Cable Trench Replacement
Cable Trench Replacement
PROJECT SNAPSHOT
Project Name | Cable Trench Replacement
Owner | ENMAX
Client’s Name | ENMAX
Location | Calgary, AB
Date / Project Timeline / Delivery | June 2021 - October 2021
Market Sector | Utilities
BACKGROUND (Pre-Project Commencement)
Replacement and installation of Plastibeton Trench sections, covers, steel supports, grounding and installation of MV Cable, MV terminations and MV Cable Testing at the below sites:
- ENMAX 2s
- ENMAX 5s
- ENMAX 6s
- ENMAX 7s
- ENMAX 9s
- ENMAX 10s
- ENMAX 11s
- ENMAX 13s
- ENMAX 21s
- ENMAX 23s
- ENMAX 24s
ACTION (ICONIC’s Scope & Delivery)
- Remove/replace damaged Plastibeton Trench Sections, and lids
- Install Plastibeton Steel Cover Supports
- Compaction and Test subgrade
- Install Grounding conductor and connect to ground grid
- Install and Terminate MV Cable (23s Only)
- VLF Cables Tests (23s Only)
RESULT / SOLUTION
- Scope was completed without incident, to client specifications.
Civil Earthworks
Civil Earthworks
PROJECT SNAPSHOT
Project Name | Civil Earthworks
Owner | City of Calgary
Client’s Name | City of Calgary
Location | Calgary, AB
Date / Project Timeline / Delivery | 2022 - Ongoing
Market Sector | Utilities
BACKGROUND (Pre-Project Commencement)
The City of Calgary requires various sized track and back hoes with a qualified operator to assist with completing various infrastructure projects. Iconic works in conjunction with The City of Calgary to complement their internal resources when required.
ACTION (ICONIC’s Scope & Delivery)
Iconic’s civil earthworks division supports The City of Calgary as needed and are responsible to:
- Have an administrative team to facilitate and manage The City’s requests efficiently.
- Receive requests from The City via telephone or email.
- Dispatch units to arrive on site on time for all requests.
- Ensure work is performed in a safe and effective manner.
- Ensure performance management of drivers, operators, and contracted staff.
- Maintain accurate records for the hours of work by employees and operators; and
- Provide accurate and timely reporting of services performed.
RESULT / SOLUTION
All projects have been completed without incident and to client specifications.
Hand Hills Substation
Hand Hills Substation
PROJECT SNAPSHOT
Project Name | Hand Hills Substation
Owner | BluEarth
Client’s Name | BluEarth
Location | Delia, Alberta
Date / Project Timeline / Delivery | April 2022 to April 2023
Market Sector | Wind
BACKGROUND (Pre-Project Commencement)
The BluEarth Hand Hills Wind Project, is a 145 MW wind project located near Delia, Alberta. This project was constructed to provide clean, renewable energy for approximately 68,000 homes annually.
ACTION (ICONIC’s Scope & Delivery)
Project Deliverables:
- Detailed Substation Engineering
- Procurement of ALL major equipment including transformer
- Site Civil Works including remediation
- Construction
- Commissioning and Start-Up
Iconic’s detailed scope of work included:
- Substation design engineering and drawing packages for construction permitting, Owner design review, installation and “as-built” documentation
- The engineering, procurement, and construction of the substation for the Project, including all civil works, structural works, and electrical works
- Engineer, supply, install, commission, and test all systems that are part of the SOW
- Construct the Work, including all site civil & structural work, foundations, laydown yards, SCADA system, mechanical and monitoring/control systems, perimeter fence.
- The furnishing and installation of the local distribution interconnection for back-up power supply during operations.
- Provide construction power.
- At Substantial Completion, furnished ALTA-equivalent surveys including an overlay of the As-Built Drawings.
- Substation construction management, including quality assurance/quality control, site health and safety, site environmental compliance, site material control and management of all subcontractors.
- Commissioning and testing including all tasks necessary to allow commissioning of the substation.
- Project turnover, including substation completion documentation, Owner training, substation operations and maintenance documentation and manuals, and procurement of Owner requested spare parts.
RESULT / SOLUTION
Project is substantially complete.
Lion's Head Xplornet Fibre EPC Project
Lion's Head Xplornet Fibre EPC Project
PROJECT SNAPSHOT
Project Name | Lion's Head Xplornet Fibre EPC Project
Owner | Hydro One
Client’s Name | Hydro One
Location | Northern Bruce Peninsula, Bruce County, ON
Date / Project Timeline / Delivery | November 2022 to December 2022.
Market Sector | Utilities
BACKGROUND (Pre-Project Commencement)
Approximately 175 poles require make-ready work for the purpose of directly accommodating Xplornet fiber attachments. The make-ready work included: replacing insulators, raising conductors, replacing cross arms, installing anchors, and replacing poles.
This work was not limited to roadside, and some off-road locations required specialized transportation equipment for access and construct.
ACTION (ICONIC’s Scope & Delivery)
175 Poles being identified as requiring “Make Ready” work (i.e. Pole Replacement, additional Guying, Grounding improvements to meet ESA regulations). Iconic is partnered with Tetra Tech on the design. Field evaluations identified various locations being in rock requiring Pickard’s to perform pole hole installations.
RESULT / SOLUTION
Project is ongoing.
Garden Plain Wind Project
Garden Plain Wind Project
PROJECT SNAPSHOT
Project Name | Garden Plain Wind Project
Owner | TransAlta
Client’s Name | TransAlta
Location | Hanna, Alberta
Date / Project Timeline / Delivery | April 2022 to April 2023
Market Sector | Utilities
BACKGROUND (Pre-Project Commencement)
The Garden Plain Wind Project is located approximately 35 km north of Hanna, Alberta. The project consists of 26 Wind Turbine Generators (WTG) for a total capacity of 130 MW, an underground collector system, a substation, and a 240 kV interconnection T-tap to an existing 240 kV transmission line.
ACTION (ICONIC’s Scope & Delivery)
- Mobilization
- Civil Works: Complete all earthwork necessary for installation of equipment, buried cables, grounding, conduits and structures; including install of foundation piles.
- Grounding Grid: Supply ground cables and all accessories for complete substation grounding grid including wires, rods, crimps and connectors, grounding mat and pigtail leads
- Main Power Transformer Foundation and Terminations: Construct the main transformer ready for final testing.
- Also construct the transformer concrete foundation and secondary containment including excavation, backfill, structural fill base, embedded steel, concrete accessories, and grounding with pigtails to grounding grid.
- Supply and install containment oil separation device including, drain, fire quenching stone and outlet drain pit.
- Structural Works: Supply and install all equipment supporting structures including associated conductor support structures whether supplied or not with equipment. Equipment includes: HV and MV breakers, HV & MV disconnects, HV surge arrestors, HV CVTs, neutral ground reactor and capacitor bank reactors.
- Electrical Works: Supply and Install Major Equipment as per project BOM.
- Control Building: Design, fabricate and shop-assemble the substation control building
- Testing and Commissioning: Complete all preliminary commissioning activities and operational tests on equipment supplied such that equipment is ready to be powered.
- Demobilization
RESULT / SOLUTION
Project completed ahead of schedule and on budget.
AML 170L Reclamation
AML 170L Reclamation
PROJECT SNAPSHOT
Project Name | AML 170L Reclamation
Owner | AltaLink
Client’s Name | AltaLink
Location | Crowsnest Pass, AB
Date / Project Timeline / Delivery | August 2022 to September 2022, completed on schedule and on budget.
Market Sector | Utilities
BACKGROUND (Pre-Project Commencement)
Iconic Power Systems Inc. (IPS) completed civil work on the 170L Urgent Line Clearance Mitigation project. IPS created access and set culverts for new structures on the partial rebuild of the 170 line in the Crowsnest Pass.
ACTION (ICONIC’s Scope & Delivery)
IPS’s Scope of Work for various structures included:
- Preparation of access road
- Stripping topsoil and subsoil and cutting in access
- Excavation and installation of culverts
- Installation of fencing and gates
- Installing grounding
Reclamation/revegetation activities included:
- Hand-seeding and raking
- Installation of erosion control blankets
- Hydromulching
- Harrow and seed
RESULT / SOLUTION
Project completed on time and on budget.
AML 113L Reclamation
AML 113L Reclamation
PROJECT SNAPSHOT
Project Name | AML 113L Reclamation
Owner | AltaLink
Client’s Name | AltaLink
Location | Canmore, AB
Date / Project Timeline / Delivery | May 2022 to July 2022, completed on schedule and on budget.
Market Sector | Utilities
BACKGROUND (Pre-Project Commencement)
Iconic Power Systems Inc. (IPS) completed reclamation work in Canmore, AB for AltaLink’s 113L transmission line rebuild project.
ACTION (ICONIC’s Scope & Delivery)
IPS’s Scope of Work for structures 1 thru 61 varied as each structure had different requirements.
- Bird sweeps
- Recontouring structure base
- Spreading topsoil and debris piles in structure workspace
- Harrow/seed disturbed areas
- Cleaning up gravel piles along the ROW
- Reclaiming access trail(s)
- Spreading pea gravel (or small crush) to walking path entrance
- Hydro-seeding
- Significant rutting on main access road required IPS to re-grade and track-pack
- Heavy decompaction (i.e. ripping/discing)
- Installing water bar channels every 15 – 20 m on significantly sloped sections
- Watercourse crossing / culvert – contour slopes, rip-rap culverts, and hydroseed / mulch crossing banks.
RESULT / SOLUTION
Project completed on time and on budget.
Anthony Henday Substation
Anthony Henday Substation
PROJECT SNAPSHOT
Project Name | Anthony Henday Substation
Owner | AltaLink
Client’s Name | AltaLink
Location | Edmonton, Alberta
Date / Project Timeline / Delivery | May 2021 to April 2022, completed ahead of schedule and on budget.
Market Sector | Utilities
BACKGROUND (Pre-Project Commencement)
Iconic Power Systems Inc. (IPS) was the Prime Contractor for this Project and responsible for the engineering, procurement, construction, installation work, and testing. The Project consisted of the construction of a new greenfield substation (309s Anthony Henday), ~50m of single circuit 138 kV transmission line, and ~70m of underground telecommunication fibre. The substation is located within the TransMountain Edmonton terminal. New major equipment included 25MVA transformers, 138 KV circuit breakers, neutral grounding resistor, control building, and 138 kV steel monopole for transmission line SOW.
ACTION (ICONIC’s Scope & Delivery)
- Procurement
- Civil works, piling, earthworks, fencing
- Grounding grid & underground conduit
- Main transformers, foundations, terminations
- Structural work
- Electrical work
- Control building
- Transmission line work
RESULT / SOLUTION
Project completed ahead of schedule and on budget.
Enfinite - eReserve 3
Enfinite - eReserve 3
PROJECT SNAPSHOT
Project Name | Enfinite - eReserve 3
Owner | ENFINITE
Client’s Name | Teric Power (designed/managed on behalf of Enfinite)
Location | Grande Prairie, Alberta, Canada
Date / Project Timeline / Delivery | May 2022 - September 2022
Market Sector | Battery Energy Storage
BACKGROUND (Pre-Project Commencement)
Iconic Power Systems Inc. (Iconic) built a Tesla MegaPack Storage Facility identical to E-Reserve 1 & 2, with the exception of layout.
The 20MW facility, located in the Grande Prairie area, features 14 Tesla Megapacks and was constructed by Iconic crews over four months.
Iconic successfully energized eReserve 3 with our partners at Enfinite and Teric Power. This marks the third successfully energized BESS by the Iconic, Enfinite and Teric Power team members
ACTION (ICONIC’s Scope & Delivery)
- Site Civil Pad Construction, including laydown and access
- Supplied all materials including structural steel skids, with the exception of major equipment
- Full Time security was engaged once civil activities were completed
- Foundations
- Installation of Fence
- Installation of Trenching and Underground Conduits
- Supplied and Installed all cables and termination kits
- Construction of Control building in Iconic yard. Iconic installed switchgear and supplied and installed all LV items.
- Shipped transformers, building and misc. equipment.
- Tesla MegaPacks were shipped to site and installed by Iconic.
- Placement of battery packs, transformers, and building
- Commissioning Support
- Fibre Work
RESULT / SOLUTION
This project was completed on time and on budget without any safety incidents.
Glenmore Line Relocation Project
Glenmore Line Relocation Project
PROJECT SNAPSHOT
Project Name | Glenmore Line Relocation Project
Owner | ENMAX
Client’s Name | ENMAX
Location | Calgary, AB
Date / Project Timeline / Delivery | August 16, 2021 - October 17, 2021 - Scope completed
Market Sector | Utilities
BACKGROUND (Pre-Project Commencement)
Enmax required underground work to install new manholes and duct bank and remove old manholes as part of re-design work near the intersection of Glenmore and 100 St SE Calgary. Iconic and its contractors worked in coordination with Enmax and Enmax contractors.
ACTION (ICONIC’s Scope & Delivery)
- Install 4 x manholes (T105) complete with grounding
- Trench approximately 430m and install duct bank
- Install secondary pedestal
RESULT/SOLUTION
Scope completed without incident to client specifications.
Meadowlark & Poundmaker Substations
Meadowlark & Poundmaker
PROJECT SNAPSHOT
Project Name | Meadowlark & Poundmaker
Owner | EPCOR
Client’s Name | EPCOR
Location | Edmonton, AB
Date / Project Timeline / Delivery | March 1, 2021 - November 25, 2021 - All construction work executed as per EPCOR schedule.
Market Sector | Utilities
BACKGROUND (Pre-Project Commencement)
As part of the WETUP (West Edmonton Transmission Upgrade Project), the Poundmaker and Meadowlark substations are being upgraded. The transmission line between the two substations is also being upgraded.
ACTION (ICONIC’s Scope & Delivery)
Meadowlark
- Excavate to develop expansion area of substation; supply and install geotextile, insulating gravel.
- Install screw pile concrete pad foundations.
- Construct 72kV gantry; install bus support steel. Install pre-cast fence and all permanent fencing.
Poundmaker
- Excavate to develop expansion area of substation; supply and install geotextile and ground grid, insulating gravel.
- Procure, delivery and install structural steel for 240kV disconnect switch, rigid bus support, and CVT support; 72kV bus support, disconnect switch, and CVT; A-frame.
- Install all permanent fencing.
RESULT / SOLUTION
All construction work executed as per EPCOR schedule.
WCSB - eReserve 2
WCSB - eReserve 2
PROJECT SNAPSHOT
Project Name | WCSB - eReserve 2
Owner | WCSB
Client’s Name | Teric Power (designed/managed on behalf of WCSB)
Location | Alberta, Canada
Date / Project Timeline / Delivery | May 2021 to October 2021 - ICONIC successfully met the October, 2021 COD target date.
Market Sector | Battery Energy Storage
BACKGROUND (Pre-Project Commencement)
Iconic Power Systems Inc. (ICONIC) was the Prime Contractor for WCSB Power to construct their second large-scale battery storage project, located in Alberta, Canada. The project consists of a 20 MW BESS utilizing Tesla Megapack batteries, providing energy balancing and grid frequency regulation services that support Alberta’s ongoing growth toward sustainable energy. eReserve 2 became commercially operational as of October 2021. As of February 2022, ICONIC has been engaged for the construction planning and execution an additional 140MW capacity spread between several new BESS facilities.
The Tesla Megapack batteries will provide various operational strategies to support Alberta’s electrical grid. These applications will focus on the delivery of sustainable energy, renewable generation smoothing, system voltage and capacity support, as well as grid frequency regulation.
ACTION (ICONIC’s Scope & Delivery)
- Site surveying and preparation;
- Access road and highway approach construction;
- Site earthworks and perimeter fencing;
- Clearing of temporary laydown areas including vehicle turn arounds and parking areas;
- Aggregate supply and hauling (site and access roads);
- Fabrication of the Megapack skids and auxiliary switching skid
- Foundation piling and Megapack skid installation;
- Trenching and cable laying (including ground grids);
- Ground preparation, setting, and installing of pre-cast transformer vaults;
- Shipment of equipment
- Placement and installation of an e-house / control building;
- Installation of 25 kV switchgear into an e-house / control building;
- Placement of all 25 kV and auxiliary transformer units;
- Placement and installation of 14 BESS units;
- Placement and installation of an auxiliary switching skid and cabinet
- Placement and installation of any site lighting and surveillance cameras (including standards or supports);
- Electrical and communication cable terminations for installed equipment (including the connection to the utility distribution feeder)
- Equipment testing;
- Pre-commissioning and commissioning support; and,
- Site clean-up and reclamation;
- Provision of materials.
As ICONIC successfully executed the eReserve 1 project in 2020, the planning and execution of eReserve 2 was further improved and streamlined.
ICONIC had to return to site to complete emergency repairs on the grounding transformer as well as cable replacement. This project was also built in central Alberta in winter conditions so ICONIC worked closely with the owner and the landowner to overcome the short construction window and challenging site conditions.
RESULT / SOLUTION
Despite a few challenges, ICONIC successfully met the October 2021 COD target date.
Blue Hill Wind Energy Project
Blue Hill Wind Energy Project
PROJECT SNAPSHOT
Project Name | Blue Hill Wind Energy Project
Owner | Algonquin Power Co.
Client’s Name | Borea
Location | Blue Hills, Near Herbert, SK
Date / Project Timeline / Delivery | March 2021 to August 2021, completed on time, without incident.
Market Sector | Wind
BACKGROUND (Pre-Project Commencement)
Located south of Herbert, the Blue Hill Wind Energy Project will be developed and operated by Algonquin Power Co. (a subsidiary of Algonquin Power & Utilities Corp.) and is expected to include up to 56 wind turbines. The turbines will add 177 megawatts of wind energy for SaskPower customers – enough energy to power more than 70,000 average Saskatchewan homes.
ICONIC was awarded this project to construct a 245kV/34.5kV Windfarm Collector Station.
ACTION (ICONIC’s Scope & Delivery)
- Trenching, install concrete trenches and conduits
- Supply and install all grounding
- Install structural steel
- Supply and install control cabling
- Supply and install signage, jb’s, yard lighting
- Offload control building and transformer
- Supply and Install Kirk Key System
- Supply and install bus and connectors
- Install miscellaneous supplied items on and in control building
RESULT / SOLUTION
Through ongoing communication and collaboration, Iconic was able to resolve challenges swiftly and focus on getting the job done safely. ICONIC delivered the collector station on time before the energization milestone date, without incident.