Civil Earthworks
Civil Earthworks
PROJECT SNAPSHOT
Project Name | Civil Earthworks
Owner | City of Calgary
Client’s Name | City of Calgary
Location | Calgary, AB
Date / Project Timeline / Delivery | 2022 - Ongoing
Market Sector | Utilities
BACKGROUND (Pre-Project Commencement)
The City of Calgary requires various sized track and back hoes with a qualified operator to assist with completing various infrastructure projects. Iconic works in conjunction with The City of Calgary to complement their internal resources when required.
ACTION (ICONIC’s Scope & Delivery)
Iconic’s civil earthworks division supports The City of Calgary as needed and are responsible to:
- Have an administrative team to facilitate and manage The City’s requests efficiently.
- Receive requests from The City via telephone or email.
- Dispatch units to arrive on site on time for all requests.
- Ensure work is performed in a safe and effective manner.
- Ensure performance management of drivers, operators, and contracted staff.
- Maintain accurate records for the hours of work by employees and operators; and
- Provide accurate and timely reporting of services performed.
RESULT / SOLUTION
All projects have been completed without incident and to client specifications.
Lion's Head Xplornet Fibre EPC Project
Lion's Head Xplornet Fibre EPC Project
PROJECT SNAPSHOT
Project Name | Lion's Head Xplornet Fibre EPC Project
Owner | Hydro One
Client’s Name | Hydro One
Location | Northern Bruce Peninsula, Bruce County, ON
Date / Project Timeline / Delivery | November 2022 to December 2022.
Market Sector | Utilities
BACKGROUND (Pre-Project Commencement)
Approximately 175 poles require make-ready work for the purpose of directly accommodating Xplornet fiber attachments. The make-ready work included: replacing insulators, raising conductors, replacing cross arms, installing anchors, and replacing poles.
This work was not limited to roadside, and some off-road locations required specialized transportation equipment for access and construct.
ACTION (ICONIC’s Scope & Delivery)
175 Poles being identified as requiring “Make Ready” work (i.e. Pole Replacement, additional Guying, Grounding improvements to meet ESA regulations). Iconic is partnered with Tetra Tech on the design. Field evaluations identified various locations being in rock requiring Pickard’s to perform pole hole installations.
RESULT / SOLUTION
Project is ongoing.
AML 170L Reclamation
AML 170L Reclamation
PROJECT SNAPSHOT
Project Name | AML 170L Reclamation
Owner | AltaLink
Client’s Name | AltaLink
Location | Crowsnest Pass, AB
Date / Project Timeline / Delivery | August 2022 to September 2022, completed on schedule and on budget.
Market Sector | Utilities
BACKGROUND (Pre-Project Commencement)
Iconic Power Systems Inc. (IPS) completed civil work on the 170L Urgent Line Clearance Mitigation project. IPS created access and set culverts for new structures on the partial rebuild of the 170 line in the Crowsnest Pass.
ACTION (ICONIC’s Scope & Delivery)
IPS’s Scope of Work for various structures included:
- Preparation of access road
- Stripping topsoil and subsoil and cutting in access
- Excavation and installation of culverts
- Installation of fencing and gates
- Installing grounding
Reclamation/revegetation activities included:
- Hand-seeding and raking
- Installation of erosion control blankets
- Hydromulching
- Harrow and seed
RESULT / SOLUTION
Project completed on time and on budget.