Wellhead Crossfield Battery Energy Storage System

Crossfield Battery Energy Storage System

Crossfield Battery Energy Storage System

PROJECT SNAPSHOT

Project Name |  Crossfield Battery Energy Storage System

Owner |

Client’s Name | Wellhead Electric (California, USA)

Location | Crossfield, AB

Date / Project Timeline / Delivery | March 2020 to December 2020, completed on time and on budget.

Market Sector | Renewable Energy, Battery Energy Storage

BACKGROUND (Pre-Project Commencement)

ICONIC was selected to handle infrastructure construction and deployment of the Battery Energy Storage Systems (BESS) for Canada’s first hybrid electric gas turbine, located in Crossfield Alberta. The project feature GE’s proven BESS systems to provide ample operating reserves – while minimizing fuel usage and Green House Gas (GHG) emissions.

The battery technology needed to be integrated into existing LM 6000 generation facilities that were already in place. During the commissioning phase, it was established that a grounding transformer was required to mitigate HV surges. This extended the schedule by two months but was vital to the safety of the people and project assets.

ACTION (ICONIC’s Scope & Delivery)

ICONIC was responsible for all installation, connection, pre-commissioning, commissioning, testing, inspection, post energization checks of the battery energy storage system. We followed GE’s detailed commissioning guidelines to ensure cells were balanced and in a safe operating state.

The BESS area pad was developed and built up to ensure proper slope and drainage. High water tables and pooling were a concern. Helical piling was determined to be the ideal solution to anchor the equipment in the existing soil conditions and to mitigate frost heave. Steel grillages were utilized to simplify the equipment connections to piling and to equipment.

Battery Energy Storage System installation scope:

  • Ground grid and testing
  • Underground & above ground conduit
  • Setting grillage onto piles
  • Cable trays installation
  • LV (<600V) power cable installation and termination
  • Instrumentation, controls, communication cables
  • MV (13.8 KV) power cables
  • Battery enclosure (HPSU’s) setting and wiring
  • Install and commission isolation and aux transformers
  • Install and commission switchgear
  • Strut supports installation
  • Cable, termination kits, load break elbows, terminals, conduit, cable tray, surge arresters

Earthworks scope:

  • Pad expansion
  • Screw pile installation
  • Trenching and backfill
  • Conduit installation
  • Fencing
  • Insulating gravel install
  • Asphalt paving

RESULT / SOLUTION

Lonnie Enns, Senior Vice President of ENMAX energy said this project reflects the transformation taking place in Canada’s energy sector, and the adoption of new and innovative solutions.

“Battery storage, combined with on-site natural gas generation provides a reliable, cost effective and sustainable method of ensuring on-demand energy. Not only will this project enable significant greenhouse gas emissions reductions, it will also provide a blueprint for further adoption in cold weather environments globally.”

ICONIC is honoured to be at forefront of BESS technology, and ensuring the required infrastructure is built to the highest safety and quality control standards.


Windrise Wind LP

Windrise Wind LP

PROJECT SNAPSHOT

Project Name |  Windrise Wind LP

Owner |

Client’s Name | TransAlta

Location | 20km south of Fort Macleod, AB

Date / Project Timeline / Delivery | April 2020 to August 2021

Market Sector | Renewable Power, Wind

BACKGROUND (Pre-Project Commencement)

Iconic Power Systems was the substation constructor on this project. We connected to AltaLink’s existing Windy Flats 138 S substation (20 minutes south of Fort Macleod, Alberta) through a 138 KV transmission line.

The project consisted of 43 Wind Turbine Generators (WTG) with a total capacity of 207 MW, an underground collector system, a substation and a transmission line. The WTGs are Siemens-Gamesa Renewable Energy (SGRE) model SG 4.8-145 AM+3 – with 90 m hub height and 145 m rotor diameter. Each has a 4.8 MW capacity rating at 60 Hz.
The scope and complexity of this project required a substation contractor with experience in renewable energy systems who was at ease managing and executing the multiple construction and electrical components.

ACTION (ICONIC’s Scope & Delivery)

ICONIC provided an integrated solution involving our Electric Utility, Distribution and Earthwork teams. The substation was to be located central to the Project, and include feeder entry breakers and disconnects, overhead bus¬es, a capacitor bank for reactive compensation, a single 230 MVA step-up transformer to 138 kV, HV metering and the transmission line breaker and disconnect. Protection, plant control and communication equipment were constructed within a modular rigid-frame steel control building located within the substation.

The scope of work included:

  • Procurement
  • Civil works, piling, earthworks, fencing
  • Grounding grid & underground conduit
  • Main transformer foundation & terminations
  • Structural work
  • Electrical work
  • Control building
  • Collector & Transmission line terminations
  • Testing & commissioning

RESULT / SOLUTION

Under ICONIC, the various project components came together like clockwork. This is reflective of our experience and familiarity working together as a consolidated unit. ICONIC’s established systems and processes enabled clear communication and efficient transitions between crews at all project stages. Over the course of a 16 month build that remained on time and on budget, there were zero safety incidents.