AML 199S EAST AIRDRIE SWITCHES AND INSULATORS
PROJECT SNAPSHOT
Project Name | AML 199s East Airdrie Switches and Insulators
Owner | ALTALINK
Client’s Name | ALTALINK
Location | Airdrie, AB
Date / Project Timeline / Delivery | Phase 1: Feb. to April 2022, Phase 2: Sept. to Dec. 2022
Market Sector | Utilities
BACKGROUND (PRE-PROJECT COMMENCEMENT)
- Capital Replacement & Upgrades Project – 199s East Airdrie
- BROWNFIELD CONSTRUCTION, TRANSFORMER REPLACEMENT, SCADA, site preparation, equipment installation, grounding, cabling, protection and control
ACTION (ICONIC’S SCOPE & DELIVERY)
- The project involved the removal and replacement of one transformer (138kV/26.5kV, 25/33/42MVA) and pad, 138kV air break switches and strain insulators, 25kV disconnect switches and bus work, and removal of concrete pads. The project also included the installation of a Spill-Chek above grade oil containment for the transformer.
RESULT / SOLUTION
- The major outages and work was completed on time with scopes relating to delayed material delivery and deficiency work completed later.