PROJECT SNAPSHOT

Project Name |  AML 113L Reclamation

Owner | AltaLink

Client’s Name | AltaLink

Location | Canmore, AB

Date / Project Timeline / Delivery | May 2022 to July 2022, completed on schedule and on budget.

Market Sector | Utilities

BACKGROUND (Pre-Project Commencement)

Iconic Power Systems Inc. (IPS) completed reclamation work in Canmore, AB for AltaLink’s 113L transmission line rebuild project.

ACTION (ICONIC’s Scope & Delivery)

IPS’s Scope of Work for structures 1 thru 61 varied as each structure had different requirements.

  • Bird sweeps
  • Recontouring structure base
  • Spreading topsoil and debris piles in structure workspace
  • Harrow/seed disturbed areas
  • Cleaning up gravel piles along the ROW
  • Reclaiming access trail(s)
  • Spreading pea gravel (or small crush) to walking path entrance
  • Hydro-seeding
  • Significant rutting on main access road required IPS to re-grade and track-pack
  • Heavy decompaction (i.e. ripping/discing)
  • Installing water bar channels every 15 – 20 m on significantly sloped sections
  • Watercourse crossing / culvert – contour slopes, rip-rap culverts, and hydroseed / mulch crossing banks.

RESULT / SOLUTION

Project completed on time and on budget.