Glenmore Line Relocation Project
PROJECT SNAPSHOT
Project Name | Glenmore Line Relocation Project
Owner | ENMAX
Client’s Name | ENMAX
Location | Calgary, AB
Date / Project Timeline / Delivery | August 16, 2021 - October 17, 2021 - Scope completed
Market Sector | Utilities
BACKGROUND (Pre-Project Commencement)
Enmax required underground work to install new manholes and duct bank and remove old manholes as part of re-design work near the intersection of Glenmore and 100 St SE Calgary. Iconic and its contractors worked in coordination with Enmax and Enmax contractors.
ACTION (ICONIC’s Scope & Delivery)
- Install 4 x manholes (T105) complete with grounding
- Trench approximately 430m and install duct bank
- Install secondary pedestal
RESULT/SOLUTION
Scope completed without incident to client specifications.