Project Name | Line Trap Insulator (Phase 1)
Owner | Hydro One
Client’s Name | Hydro One
Location | Port Carling, ON
Date / Project Timeline / Delivery | August 2022 to September 2022 on time and on budget.
Market Sector | Utilities
Construction make-ready work for joint use attachments on poles to attach fiber optic cables. In Phase 1 of this project, there were 68 H1 poles that require make-ready work
Pole Installation:
Iconic was responsible for installing 68 new poles/frame as per HONI standards.
Transformer Installation:
Iconic installed/transferred transformers .Suspect PCB transformers were returned once removed from site to the staging area at the Bracebridge OPS Centre where HONI was responsible for testing and disposal. All non-suspect transformers were returned at the end of the project to the OPS Centre.
Guying Improvements:
Iconic installed new guying as prescribed in the design. This was done under a holdoff using coverup where required and approved rubber glove techniques.
Project was completed on time and on budget without any safety incidents.