Project Name | Provost Reliability Upgrades
Owner | AltaLink
Client’s Name | Burns and McDonnell (BMcD)
Location | Near Provost, AB
Date / Project Timeline / Delivery | June 2020 to April 2021, completed on time and on budget. The project took a total of 10 months to complete.
Market Sector | Utilities
ICONIC was contracted on a project that involved a 138 KV upgrade of four AltaLink substations (Provost, Hayter, Kilarney Lake and Edgerton). The goal was to provide alternate connection points to enhance system reliability.
ICONIC’s earthworks services were utilized at the Provost substation, where the elevation of surrounding terrain was preventing proper drainage flow.
ICONIC executed 16,000 hrs on this project. Our team’s flexibility to reschedule work to match changing outage sequencing was critical to the project’s success. This was possible due our highly committed field crews, as well as our productive relationship with key players on this project. Despite the scheduling challenges, the facilities were all delivered on time, without incident.